Harnassing Innovation to Achieve Perfect Stormwater Discharge

As published in Tank Storage Magazine

One of the largest integrated midstream companies in the US implemented the latest technological innovation in stormwater discharge to improve how it operates its network of pipelines and more than 100 liquid petroleum storage terminals.

Stormwater Discharge Challenges

The company’s core values include a commitment to environmental stewardship and regulatory compliance. To align operations with these values, a regional manager decided to develop a new operational program with the following objectives:

  • Minimize labor costs associated with manual draining of secondary containment stormwater

  • Constantly filter petroleum ‘sheens’ from the stormwater

  • Eliminate the need to hire expensive vac trucks to pump, haul and treat ‘sheeny water’

  • Institute a failsafe system to prevent petroleum spills from escaping secondary containment pads

The manager said: “Over the past 20 years, our industry has experienced significant technological improvements in how we operate our pipelines and terminals. However, I was frustrated with the lack of innovation in one seemingly simple daily task – manually draining stormwater from secondary containment pads.”

Manually draining Stormwater from Secondary Containment Pads

The manager oversees scores of secondary containment pads surrounding pumping equipment, pipeline pigging stations, backup generators, additive tanks and electrical substations. These pads range in size and sump capacity from 20-gallon steel skid- mounted units to concrete containment pads with more than 10,000 gallons of sump capacity.

After more than one inch of rainwater accumulates in a containment (which occurs every nine to 10 days in his territory), the containment pads need to be drained out. The main reason is that one inch of rainwater will take up between 10% and 20% of the sump capacity of the pad. If the stormwater is not removed from the sump, there would not be enough capacity in case of a significant spill inside.

Each of these containment pads has manual valves to release excess stormwater. The discharge pipes range in size from three-quarters of an inch to four inches. However, the process for manual draining is the same for every containment:

  1. Before opening the valve, check the stormwater for a visible sheen.
  2. If there is no visible sheen, the operator can open the valve.
  3. Depending on the pipe size and amount of water, the draining process can take between five minutes to an hour for each containment.
  4. Usually, the operator has between five to 30 containment pads to drain on the same day. Typically, they open each valve and let it drain while going around to open and drain the other pads
  5. On most sites, this process requires a lot of walking over dikes, stairs, and walkways as well as ducking under other pipes to reach various pads. Experienced technicians try to develop a routine to do the process efficiently. But it’s nearly impossible to drain all the pads in a linear path without having to stand and wait for the water to run out in some of the slower-draining pipes.
  6. As a final step, the operator must make sure all the valves are closed again to protect against a spill escaping, and unfortunately, some valves do not always get closed.

Oily Sheen on Containment Stormwater

The manager explains: “We must perform daily inspections, whether it has rained or not. As a result, our team is used to walking through the entire terminal, but the process can be 200% to 500% longer after a rain. Even though it is just a cost of doing business, I always believed there had to be a better way. However, the problem is further compounded if we discover an oily sheen on the containment stormwater. It does not take much petroleum to make a sheen – just a few drips from a valve, fitting or hose.” 

Stormwater Discharge
It is illegal to release stormwater with an oily sheen.

As a result, the process is more challenging as the operator cannot discharge the contaminated water. Therefore, the following steps must be taken:

  1. Call a vac truck to pump out the containment
  2. Wait for the truck to show up
  3. Meet the truck operator for a safety briefing
  4. Accompany the vac truck to contaminated pad(s)
  5. Supervise the pumping
  6. Escort the driver back to office to complete sign out
  7. Receive and approve the invoice (usually more than $1,000)
  8. Repeat the process the next time there is a sheen

This process can take up to three hours of a technician’s time. To counteract this labor-intense manual draining, a few companies have developed petroleum filter valves.

Drawbacks of Petroleum Filter Valves

Petroleum filter valves are filled with a polymer that has two important properties:

  1. The polymer allows water to filter through on a continual basis and encapsulate an oily sheen
  2. In case of an accidental petroleum spill, the polymer would swell up and shut off all flow

In theory, it is a great idea. But, in practice, these petroleum filter valves have four main drawbacks:

  • Bulky: They take up a lot of space. Unfortunately, most containment pads are in tight quarters.

  • Sediment: Spalling concrete, decaying leaves, algae, rust, and paint chips clog the filters prematurely.

  • Slow: Each rain event only provides minimal head pressure needed to facilitate the filtration process.

  • Expensive: They range in price from $750 to more than $2,500 each.

Stormwater Discharge Sediment
Sediment and oily debris cause petroleum filter valves to fail prematurely.

The manager says that two different versions of petroleum filter valves were initially used. “They worked fine for the first week or two, but by the end of the first month, their flow rates dropped to a trickle, and our containment pads filled up with stormwater. Changing out the petroleum valves at $1,000 each was cost-prohibitive. We decided to go back to the old manual way of draining. However, when we heard that HalenHardy was working on a new petroleum valve and pre-filter system design, I was interested.

Stormwater Discharge Solutions

Talking about the company’s solution, Donny Beaver, partner at HalenHardy, says: “Our development team was originally challenged by a large electric utility to see if we could help them prevent their $2,500 petroleum filter valves from clogging. We got hold of about a half dozen plugged valves and discovered that more than 90% of their clogging was due to sediment, not oily sheen. So, we focused on solving the sediment problem first.”

However, the sediment proved to be more problematic to control and capture than the company initially thought. “We live in the mountains of Pennsylvania, and we have dramatic seasonal changes from the torrential April rains, the pollen in May and June, the scorching July sun, the falling leaves in November to the deep freeze of winter. Concrete cracks and chips. Leaves decay. Algae grow in containment shaded by pipes and tanks. It seems like a never-ending barrage of detritus in a stormwater soup.”

Fortunately, the terminal operator had a containment pad located a short distance from the development team’s lab.  They were able to gain daily access to the pad and experiment in real-world conditions. Pat Healey, R&D team specialist, adds: “We try to simulate mother nature in the lab, but we prefer to develop our products on actual job sites. As fate would have it, we picked the rainiest year on record for field testing. It was both horrible and great at the same time. We learned so much in record time.”

The Results

It became evident early on in the process that a single-stage filter (like those in other petroleum valves) was not the answer. After testing more than 80 different products in hundreds of different combinations, the research team settled on a four-stage pre-filter system.

  • STAGE 1:
    Spilltration pads to capture petroleum leaks and drips at the source of valves and fittings. This drastically reduces the oily sheen upstream from the containment outlet.
  • STAGE 2:
    Outer barrier filter socks to slow down the stormwater, stop the debris and cause 80% of the sediment to ‘drop out’.
  • STAGE 3:
    An inner filter sock barricade to remove fine sediment and suspended solids (and hold the final filter fabric securely in place).
  • STAGE 4:
    A proprietary filter fabric to capture super-fine suspended solids and additional oily sheen.

Healy says: “We discovered these four stages of pre-filtration extended the life of petroleum filter valves by 200% to 300%.”

The Bonus

While performing the tests, the research team also discovered a solution to reduce the size of petroleum filter valves by 400% and increase the filtration rate fivefold. “Containment pads offer very low head pressure as rainwater pours in. The old filter valves were designed for higher head pressure,” Beaver says. “We did some innovative tweaking of the polymer media sizes, shapes, and layering to allow us to get outstanding flow rates at just one inch of head pressure. And we still maintain a failsafe valve shutoff in case of spills. It is a win-win.”

The manager concludes: “Halen Hardy tested on our site in the worst conditions for eight months before they offered final recommendations. They gave us two options:”

  1. A do-it-ourselves option with all the training and support we would need
  2. A monthly maintenance plan where HalenHardy does all the work

“We opted for the service agreement, and after six months, it’s working like a charm. We even had an accidental overnight spill of about 50 gallons of diesel at one of our pig launching pads and the Drainiac filter valve shut off, just like it was supposed to. Not one single drop of diesel escaped the pad. I couldn’t be happier.”

Related Articles

HalenHardy® © 2022, All Rights Reserved | Privacy | Terms of Use